Water Desalination Plant, Bahrain

ASG(through Hydromagx) designed and delivered a temporary 2-Pass RO plant to a major oil refinery in the Middle East. ASG worked closely with the refinery’s operational team to meet their critical requirement to provide 1640m³ of water with a TDS of less than 10 parts per million (ppm), down from the original level of 45,000 ppm (TDS is a measure of the inorganic salts and small amounts of organic matter present in solution water). To produce the required 1640m³ of high quality water, ASG installed a 2-Pass RO system in 12 containerized modules. This meant that 8,600m³/day of sea water were treated by the RO units (10 x 40 foot containers) for the 1st pass and 2,000m³/day of brackish water Reverse Osmosis units (2 x 40 foot containers) for the 2nd pass.